Some new points of the:

Circular No. 05/2025/TT-BCT⚠️ - New regulations on technical requirements for power transmission and distribution systems

on replacing of:
  • Circular No. 39/2022/TT-BCT⛔ - Amendments to regulations on power plants
  • Circular No. 30/2019/TT-BCT⛔ - Amendments to regulations on electricity transmission system
  • Circular No. 25/2016/TT-BCT⛔ - New regulations on electricity transmission system
  • Circular No. 42/2015/TT-BCT⛔ - Regulations on electrical measurement in electricity system
  • Circular No. 39/2015/TT-BCT⛔ - Voltage quality regulations
Effective date: 01-Feb-2025
What's new
The following regulations are completely new, only in Circular 05/2025/TT-BCT and do not appear in the replaced documents:
Impact reliability of the protection relay system (Article 26.7*): The impact reliability of the protection relay system is not less than 99%.
Equipped with a phase angle measuring device (PMU) (Article 26.8.c*): A power plant with a total installed capacity of 300 MW or more must be equipped with a device with a phase angle measurement (PMU) function.
Communication transmission time for line protection relays (Article 26.8.e and Article 27.7.a*): Power transmission lines with a voltage of 220 kV or more connected to generating units or distribution yards of power plants must have 02 independent communication channels serving the transmission of protection relay signals between two ends of the line with a transfer time not greater than 20 ms.
Damping ratio (Article 37.8*): Generating units of power plants with a capacity of over 30 MW must be equipped with Power System Stabilisers (PSS) capable of degrading fluctuations with frequencies in the range from 0.1 Hz to 5 Hz, contributing to improving the stability of the power system. The generating unit must install and calibrate the parameters of the PSS equipment to ensure that the PSS equipment has a damping ratio of not less than 5%.
• Requirements for Storage Battery Systems (Article 44). This is a completely new item due to the specific regulations on the specifications and operational requirements of the BESS energy storage battery system connected to the grid.
• Record of inspection of conditions for electrification of connection points (Article 50, Article 58) requires a record of acceptance with signatures certifying eligibility for electrification of connection points to continue the steps of electrification and commissioning.
Explanations of terms related to power metering (Article 3*): Terms such as "Current Variable (CT)", "Voltage Variable (VT)", "Metering Database", "Metering Meter", "Metering System Investment Unit",... are defined more clearly and in detail.
Requirements for password layers and security of metering information (Article 99*): Specific regulations on the classification of meter passwords (Setting password, Time Sync password, Read-Only password) and management and security responsibilities for each type of password.
Changes
The following table summarizes the main changes between Circular 05/2025/TT-BCT and the replaced documents:
SpotlightOldNew
Definition of Solar Power Plant Rated CapacityThere is no clear definition yet.The maximum alternating current power capacity of the plant is calculated and announced, in accordance with the DC power capacity of the solar power plant according to the plan (Article 3.6).
Frequency ControlFrequency control in the power system (hereinafter abbreviated as frequency control) is the control process in the power system to maintain the stable operation of the system, including primary frequency control and secondary frequency control.The process of controlling the frequency of level 3 (Article 3.14.c) is added to bring the frequency of the power system to operate stably according to current regulations and ensure the economic allocation of generating capacity for generating units.
Inverse Order Component of Phase VoltageThe inverse order component of the phase voltage must not exceed 3% of the nominal voltage for the nominal voltage levels in the transmission power grid.The inverse order component of the phase voltage must not exceed 03% of the nominal voltage for high-voltage and ultra-high-voltage levels, or 05% of the nominal voltage for medium-voltage and low-voltage voltage levels (Article 7.1).
Frequency range to maintain the operation of wind and solar power plantsThere is no specific maintenance time for each frequency band.Stipulating the minimum time of maintaining the operation of power generation of wind power plants and solar power plants corresponding to the frequency bands of the power system (Article 40.2, Article 41.2).
Relative slope of a static linear lineThere is no regulation on the relative slope of a static lineWind power plants and solar power plants are capable of reducing their effective capacity according to the relative slope of the droop characteristics in the range from 02% to 10% (Article 40.3, Article 41.3)
Reactive voltage and power control modeNo regulation on voltage control mode and reactive powerWind power plants and solar power plants are capable of controlling voltage and reactive power according to the following modes: Voltage control mode according to voltage set values, voltage control mode according to voltage regulation slope characteristics (voltage/reactive power relationship characteristics), control mode according to the reactive power setting, control mode according to power factor (Article 40.5, Article 41.5).
Maintain power generation operation corresponding to the voltage rangeThere is no regulation on thresholds and maintenance times for each voltage range.Wind power plants and solar power plants at all times that are connected to the grid must be able to maintain power generation operations corresponding to the voltage range at the high-voltage side of the booster transformer of the power plant during the period (Article 40.6, Article 41.6).
Removal points
Circular 05/2025/TT-BCT has removed a number of regulations compared to the replaced documents, specifically:
• The contents of connection for selling electricity to customers connecting to medium voltage or lower in Circular 39/2015/TT-BCT: Circular 05/2025/TT-BCT does not have separate regulations on the order, procedures and technical requirements for the connection to customers using low-voltage and medium-voltage electricity as prescribed in Circular 39/2015/TT-BCT fix. This can be understood to mean that this type of connection will be in accordance with general regulations or there will be other documents regulating it.
• Abolition of the responsibility to report to the Electricity Regulatory Authority on each type of incident and impact. In previous Circulars, the responsibility to report to the Electricity Regulatory Authority is very specific about types of incidents.
• Detailed procedures for testing and test supervision: Circular 05/2025/TT-BCT only stipulates general requirements for equipment testing without going into detailed procedures.
Important Note: This is an analysis based on the information provided. For the most accurate and complete information, please refer directly to Circular 05/2025/TT-BCT and the replaced documents.