Some new points of the:

Circular No. 08/2026/TT-BNNMT - New regulations on management of irrigation works

on replacing of:
  • Circular No. 05/2018/TT-BNNPTNT⛔ - All irrigation projects must have an operating process
Effective date: 26-Jan-2026
New Features
◦ Article 2. Explanation of Terms: Circular 08/2026 adds new concepts:
◦ Reference markers are existing or newly erected markers used to replace boundary markers in cases where boundary markers cannot be erected as prescribed.
◦ Submerged channels are open water channels with a design water level lower than the average natural ground level in the surrounding area; their construction requires excavation below the natural ground level.
◦ Basic irrigation surveys involve investigating and collecting information and data on irrigation activities to serve industry statistics, decision-making in management, policy and strategy development, planning, direction, operation, and scientific research.
◦ Articles 18 and 19. Organization of basic irrigation surveys, Requirements for boundary marker placement: Circular 08/2026 supplements the regulations:
◦ Data and results from basic irrigation surveys are published, made public, and encouraged to be shared on digital platforms as regulated.
◦ If the project already has land clearance markers, water source protection corridor markers, or markers of other projects, these markers shall be considered as reference markers to determine the boundaries of the project's protection zone.
◦ Article 23. Approval of the plan and budget for boundary marker placement: Circular 08/2026 supplements the following regulations:
◦ For the item of marking boundary lines within a construction investment project, the authority to approve the budget shall be in accordance with the law on construction.
◦ For boundary marker placement items not included in construction investment projects, the project management authority or the organization/individual operating the irrigation works shall approve the boundary marker placement cost estimate when assigned the task by the owner.
◦ For boundary markers within the construction land area already allocated by the competent authority, the investor shall prepare and approve the boundary marker placement plan and organize its implementation.
◦ Article 33. Transfer and revocation of management and exploitation rights for small-scale irrigation works and on-farm irrigation works constructed with state capital: Circular 08/2026 supplements detailed regulations on the transfer and revocation of management and exploitation rights for small-scale irrigation works and on-farm irrigation works constructed with state capital.
◦ Article 34. Effective Date:
◦ Decisions approving the operating procedures and boundary marker placement plans are issued in both paper and electronic forms. Decisions approving the operating procedures and boundary marker placement plans bearing a valid digital or electronic signature from the competent authority through the online public service system have the same legal validity as paper copies and can be legally used in accordance with the law.
Changes
FocusOld (Circular 05/2018/TT-BNNPTNT)New (Circular 08/2026/TT-BNNMT)
Scope of ApplicationArticle 1: Regulations on the establishment, promulgation, and implementation of operating procedures for irrigation works; points for receiving and delivering irrigation products and services; marking the boundaries of protected areas for irrigation works; management and exploitation of small-scale and on-farm irrigation works.Article 1: Adds the following contents: organization of basic irrigation surveys; transfer and recovery of management and exploitation rights for small-scale and on-farm irrigation works constructed with state capital. Adds Clause 2: Technical operating procedures for irrigation works that are part of the technical design and implemented according to construction law are not within the scope of this Circular.
Explanation of Terms - Irrigation Works Operation ProcedureArticle 2.1: The irrigation works operation procedure is a document specifying the principles, responsibilities, implementation organization, operating sequence, and technical parameters of irrigation works serving agricultural production, people's livelihoods, and other economic sectors; ensuring that the works operate according to their design capacity and safely, harmonizing the interests between different water usage needs (hereinafter referred to as the Operation Procedure).Article 2.1: The irrigation works operation procedure (hereinafter referred to as the operation procedure) is a document specifying the principles, responsibilities, implementation organization, and operating sequence of irrigation works belonging to the irrigation system, ensuring that the irrigation system operates safely, according to its design tasks, in accordance with water resource conditions, and distributes water economically, efficiently, and harmoniously, harmonizing the interests between different water usage needs.
Document for Appraisal of Operating ProceduresArticle 7.1: Organizations and individuals requesting approval of operating procedures for irrigation works shall submit a dossier including one paper copy and one electronic copy directly or by mail to the receiving agency as prescribed in Clause 3 of this Article.Article 7.1: Organizations and individuals shall submit one set of documents requesting approval of operating procedures in person at the One-Stop Service Center; online at the National Public Service Portal; or via postal service to the receiving agency as prescribed in Clause 3 of this Article. Changes to the submission method: from one paper copy and one electronic copy to one set of documents submitted directly, online, or by mail.
Agency for Assessing Operational ProceduresArticle 7.3: a) The General Department of Irrigation receives dossiers and organizes the assessment of operational procedures for particularly important irrigation works and works whose exploitation and protection involve two or more provinces; b) The Department of Agriculture and Rural Development receives dossiers and organizes the assessment of operational procedures for irrigation works in its area, except for cases specified in point a of this clause and small irrigation works. c) The specialized agency for state management of irrigation at the district level is the focal point for receiving dossiers and organizing the assessment of operational procedures for works approved by the People's Committee of the district level.Article 7.3: a) The Department of Irrigation Works Management and Construction receives dossiers and organizes the assessment of operational procedures under the approval authority of the Minister of Agriculture and Environment. b) The Department of Agriculture and Environment receives dossiers and organizes the assessment of operational procedures under the approval authority of the Chairman of the People's Committee of the province. c) The specialized agency with state management functions in agriculture and environment at the commune level receives the dossier and organizes the assessment of the operational process approved by the Chairman of the People's Committee at the commune level. The name of the assessing agency is changed from the General Department of Irrigation to the Department of Irrigation Works Management and Construction, and from the Department of Agriculture and Rural Development to the Department of Agriculture and Environment.
Authority to approve operating proceduresArticle 9.1: The Ministry of Agriculture and Rural Development approves the operating procedures for particularly important irrigation works and works whose exploitation and protection involve two or more provinces.Article 9.1: The Minister of Agriculture and Environment approves the operating procedures for particularly important irrigation works and irrigation works whose exploitation and protection involve two or more provincial-level administrative units. The authority to approve is changed from the Ministry of Agriculture and Rural Development to the Minister of Agriculture and Environment.
Basic Irrigation SurveyNot mentionedArticle 18: Supplementing regulations on the organization of basic irrigation surveys.
Document for Boundary Marking PlanArticle 21: Investors, organizations, and individuals exploiting irrigation works as stipulated in Clauses 1 and 2 of Article 43 of the Law on Irrigation shall submit a dossier including one paper copy and one electronic copy directly or by mail to the receiving agency as prescribed in Clause 2 of Article 22 of this Circular.Article 22: Investors, organizations, and individuals exploiting irrigation works as stipulated in Clauses 1 and 2 of Article 43 of the Law on Irrigation shall submit one set of documents directly at the One-Stop Service Center, online at the National Public Service Portal, or via postal service to the receiving agency as prescribed in Clause 2 of Article 23 of this Circular. Change in the submission method: from one paper copy and one electronic copy to one set of documents submitted directly, online, or by mail.
Approval of Boundary Marking PlanArticle 22: 3. Time for Appraisal and Approval a) Within 3 working days from the date of receiving the dossier, the Department of Agriculture and Rural Development is responsible for reviewing and checking the dossier; if the dossier is invalid, it must notify the organization or individual preparing the dossier to complete the dossier according to regulations; b) Within 30 working days from the date of receiving a complete and valid dossier, the Department of Agriculture and Rural Development is responsible for appraising the dossier and obtaining opinions from relevant agencies and units. If the conditions are met, the Department of Agriculture and Rural Development shall submit the plan for marking the boundaries of the protected area of irrigation works to the Provincial People's Committee for approval; if the conditions are not met, the reason shall be notified to the organization or individual.Article 23: 3. Time for Appraisal and Approval: a) The agency receiving the dossier shall immediately respond regarding the completeness of the dossier in the case of direct submission; a) A written response will be provided within one working day if the application is incomplete for online or postal submissions. If the receiving agency receives the application after 4 PM, the response will be sent on the next working day; b) Within 18 working days from the date of receiving a complete application as prescribed, the receiving agency will organize the assessment and submit it to the competent authority for consideration and approval. If the application does not meet the approval requirements, the receiving agency will notify the applicant in writing and return the application for supplementation and completion. Changes to the assessment and approval timeframe will also be addressed.
Establishment and Strengthening of Grassroots Irrigation OrganizationsArticle 30.1: Within a period not exceeding 3 years from the effective date of this Circular, the Provincial People's Committee shall direct relevant agencies and units to develop plans and organize the implementation of establishing and strengthening grassroots irrigation organizations, specifically:Article 31.1: The Provincial People's Committee shall direct relevant agencies and units to develop plans and organize the implementation of establishing and strengthening grassroots irrigation organizations, specifically: The provision regarding the 3-year period from the effective date of this Circular is removed.
Article 32. Transitional ProvisionsArticle 32.1: Irrigation works currently in operation that do not yet have an operating procedure must have one approved by the competent authority no later than 3 years from the effective date of this Circular, except for small irrigation works. Article 32.2: For reservoirs currently in operation that do not yet have an operating procedure, the deadline for having an operating procedure approved by the competent authority shall be in accordance with the Government's regulations on dam and reservoir safety management.Article 35.1: For irrigation works whose operation and protection involve two or more provincial-level administrative units that change after the reorganization of provincial-level administrative units, the agency or organization currently managing the irrigation works shall continue to manage and operate them until a decision is made by the competent authority. Article 35.2: Provincial People's Committees shall review, finalize, and approve the operating procedures in their respective areas in accordance with the provisions of this Circular, no later than three years from the effective date of this Circular. Article 35.3: The locations of irrigation product and service delivery points that were determined before the effective date of this Circular shall continue to be implemented. Article 35.4: The plan for marking the boundaries of irrigation works that were approved before the effective date of this Circular shall continue to be implemented. [Completely changes the content of the transitional provisions]
### Removal Points
◦ Article 17. Authority to decide on the decentralization of management of irrigation works and the location of delivery points for irrigation products and services: Circular 08/2026 no longer specifically regulates the authority to decide on the decentralization of management of irrigation works and the location of delivery points for irrigation products and services as in Circular 05/2018.
◦ Article 32. Transitional Provisions: Circular 05/2018 stipulated the deadline for operating irrigation works to have approved operating procedures. Circular 08/2026 repeals this provision and replaces it with other transitional provisions related to the reorganization of administrative units, review of operating procedures, and continued implementation of the old regulations on handover points and boundary marking plans.
◦ Circular 08/2026 removes Appendices I and II issued with Circular No. 20/2025/TT-BNNMT: relating to the delegation, decentralization, and delineation of state management authority in the field of irrigation.