Some new points of the:

Decree No. 274/2026/NĐ-CP - New regulations on bidding for business investment projects

on replacing of:
  • Decree No. 225/2025/NĐ-CP⛔ - Amendments to regulations on bidding for investor selection
  • Decree No. 115/2024/NĐ-CP⛔ - Regulations on bidding in relation to investment projects involving land use, applicable from September 16, 2024
  • Decree No. 23/2024/NĐ-CP⛔ - New regulations on bidding on selection of investors
Effective date: 21-Aug-2026
What's new
(Completely new regulations only appear in Decree No. 274/2026/ND-CP, not in old documents)
1. Supplementing the mechanism for deducting infrastructure construction costs for BT projects:
◦ Content: Decree No. 274/2026/ND-CP supplements detailed guidance clauses on the case where the land fund has not yet invested in infrastructure but must use the land price in the land price list including infrastructure (or similar areas) to determine the value, the cost of infrastructure construction is deducted based on the investment capital rate or areas with similar conditions.
◦ Legal basis: Article 74 (Amending and supplementing Article 6 of Decree No. 257/2025/ND-CP).
2. Regulations on handling situations when there are changes in the arrangement of administrative units:
◦ Content: Supplementing criteria and methods of determining reference projects, minimum budget payment rate ($m$) in case localities rearrange provincial-level administrative units (division, separation, merger before and after 01/07/2025), helping localities have a unified basis for calculation.
◦ Legal basis: Article 52, Clause 5.
3. Inheritance of capacity for branches/enterprises/representative offices separated from legal entities:
◦ Content: For the first time, the legal situation is clearly defined: In case a branch, enterprise or representative office is separated from a legal entity in accordance with civil law, the investor receiving or forming from these units may inherit the bidding capacity that such units have previously performed.
◦ Legal basis: Article 63, Clause 11.
---
Changes
(The provisions are in both old and new documents but have been amended and adjusted in Decree No. 274/2026/ND-CP)
FocusOld (Decree No. 23/2024/ND-CP, 115/2024/ND-CP and 225/2025/ND-CP)New (Decree No. 274/2026/ND-CP)
Provincial Investor Selection Results/Bidding DocumentsThe Department of Planning and Investment assumes the prime responsibility for organizing the appraisal of the contents under the competence of the Chairman of the Provincial People's Committee.Transfer of authority to Department of Finance provinces and centrally-run cities to carry out appraisal.
(Base: Article 62)
Time to prepare the project implementation registration dossier (E-HSDKTHDA)The minimum time to prepare the dossier is 30 days (or 30 days from the date of issuance of the E-HSMQT).Shorten the time for preparing dossiers to a minimum of 20 working days.
(Base: Article 41 Clause 1)
Time limit for handling situations when there are less than 3 investors submitting documentsThe time limit for processing is not more than 24 hours (or not more than 4 hours depending on each project) from the time of bid closing.Extend the time limit for the bid solicitor/inviting entity to handle more flexibly: no more than 03 working days
. (Base: Article 63, Clause 2)
Roadmap for applying online investor selectionApply according to the timelines of 2025 and 2026 (e.g. from 01/01/2026 or 01/09/2025 depending on the type of project).Push back and agree on a new roadmap: Starting from 01/01/2027 (submission of proposals, invitation for interest) and 01/04/2027 (official online bidding).
(Base: Article 70)
Central State Management and Inspection Agency for BiddingThe Ministry of Planning and Investment assumes the prime responsibility for inspecting and synthesizing reports.Transfer the entire function of central state inspection and management to the Ministry of Finance
. (Base: Article 64, Article 66)
---
Removal points
(Concepts, regulations or documents that exist in the old group of documents but are completely abolished, no longer appear in Decree No. 274/2026/ND-CP)
1. To annul the maintenance of two separate Decrees for projects using land and projects in sectors and domains:
◦ Content: Decree No. 274/2026/ND-CP officially consolidates all regulations on selection of investors to implement investment projects using land and projects subject to bidding under the law on management of sectors and fields into a single document. Therefore, all Decree No. 23/2024/ND-CP, Decree No. 115/2024/ND-CP and Decree No. 225/2025/ND-CP are annulled.
◦ Legal basis: Article 75, Clause 3.
2. Deletion of terms and jurisdictions related to the Ministry of Planning and Investment / Department of Planning and Investment:
Content: Due to the change in the assignment of state management functions (transfer of bidding management to the Ministry of Finance), all regulations, forms or provisions assigning responsibility to the Ministry of Planning and Investment or Department of Planning and Investment for consultation, appraisal and receipt of project proposal dossiers have been removed and replaced by Ministry of Finance and Department of Finance*.
◦ Legal basis: Throughout the Decree (expressed through the replacement of the subject in the provisions on inspection, appraisal and management of databases such as Article 62, Article 64, Article 66).
3. Removing the old transitional regulations (associated with the 2024 and 2025 milestones):
◦ Content: The transitional provisions that were temporarily applied when the new Law on Bidding 2023 came into effect (such as the milestones for handling transitional projects before 01/01/2024 or 01/08/2024 of the old decrees) have been completely removed, replaced by a system of newly standardized transitional provisions for 2026-2027.
◦ Legal basis: Article 76.