Decree No. 349/2026/NĐ-CP - Many major changes in contractor selection from September 9, 2026

Effective date: 09-Sep-2026
Limitations
The quoted price difference threshold is entitled to be excluded (Point d, Clause 2, Article 18)
The Employer reserves the right to exclude quotations or items in the quotation with a price 30% higher or lower than the average price in order to recalculate the average price more accurately.
Price limit of bidding packages applicable to contractor appointment (Clause 5, Article 78)
Qوي determine the specific ceiling price for procurement packages that do not form projects (not exceeding VND 01 billion), bidding packages for consultancy services (not exceeding VND 03 billion), and bidding packages for non-consultancy, goods, construction and installation, and mixed (not exceeding VND 05 billion) to be applied in the form of contractor appointment.
Limit on the bidding price (Point c, Clause 3, Article 79)
In the normal contractor appointment process, the bid-winning bid price of the contractor is not allowed to exceed the approved bidding package price.
Proportion of the value of substituted and supplementary goods (Clause 33a, Article 140)
For a bidding package with only one participating contractor who does not meet the technical requirements for common materials and equipment, the total value of goods items allowed to be supplemented or replaced must not account for more than 1% of the total price of the bidding package.
Maximum percentage of subcontractors (Clause 2, Article 141)
Contractors are only allowed to use subcontractors within the percentage limit of the maximum value specified by the investor in the bidding dossier or dossier of requirements.
Contract value limit when performing urgent tasks (Point d, Clause 3, Article 14 and Point c, Clause 1, Article 19)
Pending the issuance of urgent order unit prices by competent agencies, agencies and units may only sign contracts up to 90% of the order value according to the implementation price of the latest year or 90% of the assigned estimate.
Need to know
Compulsory posting of quotation request (Point d, Clause 2, Article 18)
The investor is obliged to post the request for quotation on the National Procurement Network System so that interested units can send quotations within the minimum time limit as prescribed.
Obligation to update the contract performance schedule (Clause 2, Article 35)
The investor is required to update the actual progress of contract performance when completing the specified milestones on the National Bidding Network System, and at the same time update any changes about the subcontractor.
Mandatory conditions for being proposed for contractor appointment (Point c, Clause 3, Article 79)
A contractor may only be proposed to appoint a contractor when it fully meets the core conditions, including: having a valid dossier of proposals, having the capacity and techniques to meet the requirements of the dossier of requirements, and having a bid-winning bid price not exceeding the price of the bidding package.
Responsibility for mandatory handling when personnel violate the law (Clause 2, Article 140)
When the contractor's personnel are convicted by the Court of violating regulations on bidding, causing serious consequences to win the bid, the investor is required to terminate the contract, confiscate the value of the contract performance security and post the violating contractor on the system.
Obligation to disclose information on the results of the performance of the order contract (Clause 6, Article 109)
The ordering organization is required to disclose information on the results of contract performance, progress, quality of goods and violations (if any) on the National Procurement Network System within 30 days from the end of the contract performance period.
Responsibility to settle petitions within the statutory time limit (Clause 1, Article 138)
The investor or a competent person is required to issue a written settlement of the contractor/organization's petition and publicly post it on the National Procurement Network System within 07 working days from the date of receipt of the application.