stop-check The procedure for dispatching of national power system English attachment

Circular No. 40/2014/TT-BCT dated November 05, 2014 of the Ministry of Industry and Trade on stipulating the procedure for dispatching of national power system
Posted: 17/11/2014 9:10:27 AM | Latest updated: 14/2/2025 1:47:17 PM (GMT+7)
Effective: 24-Dec-2014 Status: Expired on: 1-Feb-2025
LuatVietnam This Circular stipulates provisions on the following issues:
a) Dispatching hierarchy of the national power system;
b) Responsibility of organizations and individuals involved in the dispatching and operation of national power system;
c) Formulation and approval of operation mode of national power system;
d) Dispatching and operation of national power system in real time;
dd) Duties of divisions involved in the dispatching of national power system; operation of power plant, power station, power grid and control center;
e) Training of titles directly involved in the dispatching and operation of national power system.
Power system dispatching prescribed in this Circular is activities of direction and control of power generation, transmission and distribution process in the national power system as per the defined procedures, technical regulations and operation modes
This Circular takes effect from December 24th, 2014 and replaces Decision No. 56/QD-BCN dated November 26th, 2001 of the Ministry of Industry stipulating the Procedure for dispatching of national power system.
 
Effective notes
  • See more the amendments, supplements at Circular No. 31/2019/TT-BCT⛔ dated November 18th, 2019.
  • See more the amendments, supplements to at Circular No. 12/2024/TT-BCT⛔ dated August 01, 2024.
  • This Circular shall be expired from February 1st, 2025, replaced by Ciruclar No. 06/2025/TT-BCTstatus2 dated from February 1st, 2025.