stop-check Procedures for quality inspection of imported construction materials English attachment

Decision No. 251/ QD-BXD⛔ dated February 27, 2026 of the Ministry of Construction on the announcement of newly issued administrative procedures in the field of construction materials under the management of the Ministry of Construction (13 pages)
Posted: 2/3/2026 8:02:28 AM | Latest updated: 3/7/2026 7:28:49 AM (GMT+7) | Newsletter #:6390
Effective: 27-Feb-2026 Status: Expired on: 1-Jul-2026
This Decision is announced with instructions on procedures "Quality inspection of imported group 2 construction materials" (based on the provisions of Circular No. 10/2024/TT-BXD⛔ dated 01/11/2024).
The specific contents are as follows:
1. Procedure
This procedure is divided into two main cases: pre-clearance inspection and post-clearance inspection.
a) For goods inspected for quality BEFORE customs clearance:
• Step 1: Importers submit inspection registration dossiers to the quality inspection agency (Department of Construction).
• Step 2: The inspection agency receives and processes the dossier:
◦ Check the completeness and suitability of the dossier (Certificate of conformity, seal of conformity, label of goods, certificate of quality, etc.).
◦ If the dossier is valid: Within 01 working day, issue a "Notice of inspection results to meet quality requirements" for the importer to carry out customs clearance procedures.
◦ If the application is invalid:
◦ Errors in goods labels: Issue a notice of failure to meet the requirements and request for remediation within 05 working days. Issue a satisfactory notice only after there is remedial evidence.
◦ Inappropriate quality certificate: Issue a notice of failure to meet the requirements, send it to the customs authority and the importer, and report to the competent authority for handling.
◦ Incomplete Documents: Additional importers are required within 15 working days. If the deadline is overdue and not supplemented, the inspection agency will issue a notice "The shipment does not complete the dossier" and may conduct an unscheduled inspection.
b) For goods inspected for quality AFTER customs clearance:
• Step 1: Within 01 working day, the inspection agency confirms that it has registered for inspection. The importer submits this registration to the customs office for customs clearance of goods.
• Step 2: After customs clearance, the importer must submit the following documents to the inspection agency:
◦ Within 15 working days (or 35 days for cement and additives), submit a true copy of the Certificate of Conformity and quality inspection results.
◦ If the goods have been certified in the exporting country, within 03 working days, submit a true copy of the Certificate of conformity with technical regulations.
• Responsibility: The importer is fully responsible for the quality of the goods and must voluntarily handle and recall if the goods are not suitable.
2. How it works
• Main: Submit documents online via the National Single Window Portal or the National Public Service Portal.
• Backup: If the system has a problem, paper documents can be submitted directly at the Public Administration Service Center.
3. Composition, number of applications
• Quantity: 01 set.
• Components of the dossier include:
◦ Registration form for quality inspection (according to Form No. 01).
◦ A copy of the contract and list of goods (if any).
◦ Copies of bills of lading, invoices, declarations of imported goods (if any).
◦ A copy of the quality certificate of the exporting country (if any).
◦ Copy of certificate of origin (C/O), certificate of free sale (CFS) (if any).
◦ Photos or descriptions of goods, labels and sub-labels.
◦ Certificate of conformity (in case of post-customs clearance inspection).
4. Settlement Deadline
• 01 working day, from the date of receipt of a complete and valid dossier.
5. Target audience
• Organizations and individuals importing construction materials.
6. Resolution Agency
• Agencies directly settling: Department of Construction (where the enterprise registers its business, where the border gate is located, or where customs procedures are carried out).
7. Results
• Notification of results of quality inspection of imported goods (according to Form No. 03).
8. Fees and charges
• None.
9. Name of application form, declaration
• Form No. 01: Registration for state inspection of quality of imported goods.
• Form No. 02: Receipt of the inspection registration dossier.
• Form No. 03: Notification of results of quality inspection of imported goods.
10. Requirements and conditions for implementation
• Imported construction material products and goods must be on the list specified in the National Technical Regulation QCVN 16:2023/ BXDstatus2 .
• Goods must be registered for inspection and committed to quality in accordance with regulations and standards based on the results of technical-regulation conformity certification of organizations designated by the Ministry of Construction.
The Decision takes effect from the date of signing.
 
Effective notes
Expire from July 1, 2026, replaced by Decision No. 1095/ QD-BXD dated June 30, 2026.