Some amends and supplements of the

Circular No. 16/2025/TT-BCT⛔ - New regulations on registration to participate in the electricity market from February 1, 2025

within:
  • Circular No. 36/2025/TT-BCT⛔ - Amendments to regulations on operation of the electricity wholesale market
  • Effected from: 03-Jun-2025
    New additions
    ◦ Article 3, Clause 1, Point b (amended Clause 2, Article 3 of Circular 16): Add a clear definition of "The amount of electricity output operated and mobilized corresponds to the maximum level according to the gas supply capacity..." in the concept of "undertaking".
    ◦ Article 3, Clause 2 (supplement Clause 19a, Article 3 of Circular 16): Add a specific definition of "Gas-fired thermal power plants are required to make maximum use of gas fuel sources", along with citations to relevant Decrees.
    ◦ Article 132, Clause 4 (supplement Clause 4, Article 132 of Circular 16): Clearly stipulates the responsibility of Vietnam Electricity Group or the electricity wholesaler in providing data on consumption to the Power System Operator and the electricity market.
    ◦ Article 132, Clause 5 (supplement Clause 5 Article 132 of Circular 16): Clearly stipulates the responsibilities of Power Generation Units and Fuel Supply Units in providing data on gas supply capacity and fuel requirements of Thermal Power Plants that are required to use maximum gas fuel sources for the Power System Operator and the electricity market.
    ◦ Article 133, Clause 4a (supplement Clause 4a, Article 133 of Circular 16): Specific regulations on the roadmap and mobilization methods for hydropower plants operating in coordination with multi-purpose strategic hydropower plants during the period of not directly participating in the electricity market (before June 1, 2026).
    ◦ Article 1, Clause 22: Add Appendix VI to Circular No. 16/2025/TT-BCT
    ◦ Article 1, Clause 17 (supplement Clause 4a, Article 133 of Circular 16): During the period of not directly participating in the electricity market, these hydropower plants are mobilized as power plants indirectly participating in the electricity market.
    ### Changes
    FocusOldNew
    Scope of adjustment of hydropower plantsb) Power plants with a designed capacity of 10 MW or more whose power purchase contracts based on avoided costs expire, including cascade (for hydropower) and power plants using other renewable energy... Article 4, clause 1b) Power plants with an installed capacity of 10 MW or more whose power purchase contracts based on avoided costs expire, including cascade hydropower plants and power plants using other renewable energy... Article 4, clause 1
    Type of BOT factoryThis phrase is not included in the amendment Article 4, Clause 1"Design capacity" is changed to "Installed capacity" Article 4, Clause 1
    BOT plant typeThermal power plants are required to make maximum use of gas fuel sources and are allowed by competent state agencies to indirectly participate in the electricity market; Article 4, paragraph 3Gas-fired thermal power plants are required to make maximum use of gas fuel sources Article 4, paragraph 3
    Scope of application of Article 11...not completing registration to participate in the electricity market, power plants without a Power Purchase Agreement... Article 11, Clause 1...not completing registration to participate in the electricity market (except for hydropower plants that coordinate operations with multi-purpose strategic hydropower plants as prescribed in Clause 4a, Article 133 of this Circular), power plants without a Power Purchase Agreement... Article 11, Clause 1
    Order of mobilization when overloaded, surplus sourcea) Reduce the generating capacity of thermal power plants with variable costs in order from high to low Article 18, clause 3a) Reduce the generating capacity of thermal power plants with variable costs in order from high to low, except for thermal power plants of gas-fired thermal power plants that are required to make maximum use of gas fuel sources Article 18, clause 3
    Order of mobilization in case of overload or excess powere) Reducing part or all of the wind power plant, grid-connected solar power plant (except for power plants under Point h, Clause 3 of this Article);... Article 18, Clause 3e) Reducing part or all of the wind power plant, grid-connected solar power plant (except for power plants under Point k, Clause 3 of this Article);... Article 18, Clause 3
    Order of mobilization when overloaded, excess sourceAdd more linesg) Reduce the generation capacity of thermal power units of gas-fired thermal power plants that are required to use gas fuel to the maximum; h) Stop thermal power units of gas-fired thermal power plants that are required to use gas fuel to the maximum with variable costs in order from highest to lowest; Article 18, Clause 3
    Order of mobilization in case of overload or excess sourceProportional reduction4. For generators of power plants belonging to the same group at points e, g, i and k, Clause 3 of this Article, the reduction of generating capacity is carried out according to the principle of evenly distributing the capacity to be reduced according to the ratio of rated capacity, available capacity, announced capacity or forecast capacity (depending on the type of power source and dispatch method), regardless of price criteria Article 18, Clause 4
    Constraints in power system operationGuarantee constraintsConstraints on underwriting Article 19, Clause 2
    Amendment and supplement to Article 32- Solutions to ensure stable, safe and reliable operation of the power system- Solutions to ensure stable, safe and reliable operation of the power system. Water value and optimal water level of cascade hydropower plants and hydropower plants with reservoirs regulating for 2 or more days per week in the coming month; Article 42, Clause 1
    ### Abolished or expired
    ◦ Article 2, Clause 1: Abolish point c, Clause 1, Article 17 of Circular 16.
    ◦ Article 2, Clause 2: Abolish Clause 15, Article 54 of Circular 16.
    ◦ Article 2, Clause 3: Abolish Clause 15, Article 60 of Circular 16.
    ◦ Article 2, Clause 4: Abolish Clause 9, Article 13, Appendix II issued with Circular 16.
    ### General comments on the impact of the difference
    ◦ Focus on Gas-fired Power Plants: The amendments and supplements mainly focus on clarifying and prioritizing gas-fired power plants that are bound to make maximum use of gas fuel sources. This demonstrates efforts to ensure the utilization of domestic gas resources and optimize the operation of gas-fired power plants.
    ◦ Specifying and detailing regulations: Circular 36/2025/TT-BCT adds more detailed definitions and regulations, making the implementation and supervision of the electricity market clearer and more effective.
    ◦ Priority of power supply and system stability: Amendments to the order of power mobilization in case of overload and excess power show high priority for ensuring stable and reliable power supply for the system, especially in the context of increasing participation of renewable energy sources.
    ◦ Impact on market operations: These changes may affect market electricity prices and payments for power plants, especially gas-fired power plants. Relevant entities need to be aware of the new regulations to ensure compliance and optimize their operations in the electricity market.
    ◦ More flexibility in dispatching Modifications from "design capacity" to "installed capacity" or the requirement to sign additional contract appendices will help the operating unit operate more easily by closely monitoring the actual electrical equipment.
    Hope this analysis provides you with insight and useful information!
    Posted date: 23-Oct-2025 23 2025 3:25PM VN
    Some new points of the:

    Circular No. 16/2025/TT-BCT⛔ - New regulations on registration to participate in the electricity market from February 1, 2025

    on replacing of:
    • Circular No. 21/2024/TT-BCT⛔ - Regulations on registration to participate in the electricity market, applicable from 25/11/2024
    Effective date: 01-Feb-2025
    What's new
    The following provisions are completely new, only in Circular No. 16/2025/TT-BCT and not in Circular No. 21/2024/TT-BCT:
    ◦ Article 2. Applicable subjects: Add the applicable subjects as "6. Large electricity users participating in the direct electricity purchase and sale mechanism."
    ◦ Article 4. Responsibilities of power generation units in participating in the electricity market:
    ◦ Clause 1.a: Add "(including BOT power plants whose contracts have expired and are transferred to Vietnam, hydropower plants jointly operated with multi-purpose strategic hydropower plants as prescribed in Point b, Clause 4, Article 51 of the Electricity Law)".
    ◦ Clause 1.c: Add "Renewable energy power plants participating in the direct electricity trading mechanism through the national grid".
    ◦ Clause 3.h: Add "Hydropower plants operating under the avoided cost mechanism with valid contracts".
    ◦ Article 11. Mobilizing power plants that have not directly participated in the electricity market: Clearly stipulates the cases and methods of mobilizing power plants that have not completed registration to participate in the electricity market, do not have a power purchase contract, do not have an electricity price, or do not have an agreement on a commercial operation date.
    ◦ Article 17. Determination of contracted electricity output: Detailed regulations on determining contracted electricity output, especially in cases where the payment output ratio according to the contract price cannot be agreed upon, adjusting the contracted electricity output per month/cycle.
    ◦ Article 18. Principles of operation and mobilization of power sources when overload or excess power occurs: Specific regulations on the order of reducing mobilization of different types of power plants when overload or excess power occurs in the power system.
    ◦ Article 29. Determining the minimum annual and minimum monthly contracted electricity output for thermal power plants with power purchase contracts with Vietnam Electricity Group:
    ◦ Clause 1.b: Supplement "For thermal power plants, offshore wind power plants, and new energy power plants that are subject to the long-term minimum contract power output mechanism according to the Regulations on power development planning, power grid development plans, investment in power project construction and bidding to select investors for power business projects and the Regulations on renewable energy and new energy power development issued by the Government shall be implemented as follows:
    ◦ Determine the total minimum contract electricity output for year N as prescribed in Point a of this Clause;
    ◦ In case the total minimum contracted electricity output in year N is lower than the long-term minimum contracted electricity output, the total minimum contracted electricity output in year N is adjusted to the long-term minimum contracted electricity output specified in the power purchase contract.
    ◦ Clause 2.c: Supplement "For thermal power plants, offshore wind power plants, new energy power plants that are subject to the long-term minimum contract power output mechanism according to the Regulations on power development planning, power grid development plans, investment in power project construction and bidding to select investors for power business projects and the Regulations on development of renewable energy and new energy power issued by the Government shall be implemented as follows:
    ◦ Determine the minimum contract electricity output for month M in year N according to the provisions at points a and b of this clause;
    ◦ In case the total minimum contract output of month M in year N is lower than the long-term minimum contract output determined for month M, the total minimum contract electricity output of month M in year N will be adjusted by the corresponding long-term minimum contract electricity output determined in the power purchase contract (if any).
    ◦ Article 50. Bidding for groups of cascade hydropower plants: Detailed regulations on the bidding method for groups of cascade hydropower plants, including the designation of a representative bidding unit.
    ◦ Article 71. Payment for exported and imported electricity:
    ◦ Payment regulations for exported and imported electricity according to contract.
    ◦ Article 74. Responsibility for collecting and managing metering data in the electricity market:
    ◦ Clearly stipulate that the power system and electricity market operators synchronize and send metering data to the shared metering data warehouse of Vietnam Electricity Group.
    ◦ Article 77. Confirmation of electricity output according to meter readings:
    ◦ Requires digital signature to verify meter readings.
    ◦ Article 88. Electricity output of power plants serving payment in the electricity market:
    ◦ Clause 1.a: Add "(Qbp)".
    ◦ Clause 2.c: "In case there is no dispatch order in transaction cycle i, Qdd is determined according to the formula: Qddi = Average mobilized capacity (MW) x ∆T",
    ◦ Detailed regulations on calculating the difference in generated electricity output compared to the output mobilized according to the dispatch order.
    ◦ Article 89. Adjusting the electricity output of power plants for payment in the electricity market: Stipulates the principles for adjusting the additional electricity output (Qconi) and the electricity output paid according to the offered price for plants with an offered price higher than the ceiling price of the electricity market (Qbpi).
    ◦ Article 99. Payment for renewable energy power plants directly participating in the electricity market:
    ◦ Regulations on payment for renewable energy power plants participating in the electricity market, including cases with power purchase contracts with large electricity users participating in the direct power purchase mechanism and cases not participating in the direct power purchase mechanism.
    ◦ Article 111. Handling of payment errors:
    ◦ Regulations for handling payment errors.
    ◦ Article 131. Regulations on duties, powers and responsibilities of the Electricity Market Transaction Operation Engineer:
    ### Changes
    Below is a comparison table of changes between Circular No. 16/2025/TT-BCT and Circular No. 21/2024/TT-BCT for provisions with differences:
    FocusOld (Circular 21/2024/TT-BCT)New (Circular 16/2025/TT-BCT)
    Explanation of terms (Article 3)- The number of explained terms is less.- There is no term "Direct electricity trading mechanism, state electricity management agency, large electricity customers, load block, exceeding gas fuel limit,..."- The number of explained terms is more, adding important terms such as: "Direct electricity trading mechanism, state electricity management agency, large electricity customers, load block, exceeding gas fuel limit,..."
    Subjects of application (Article 2)Applicable to units participating in the electricity market such as: Electricity wholesale buyers, power generation units, Power system and electricity market operators, power transmission units, Vietnam Electricity GroupAdd the subject "6. Large electricity users participating in the direct electricity purchase and sale mechanism"
    Responsibilities of the Power System and Electricity Market Operator (Article 4.4)Report to the Electricity Regulatory AuthorityReport to the State Electricity Management Agency
    Types of Ancillary Services (Article 22.1)Secondary frequency control, fast start, voltage regulation and black start.Secondary frequency control, fast start, voltage regulation, black start, must-run operation reserve.
    Determining monthly contract electricity output (Article 39)Only apply the formula QcM = α × QdkM (QcM: Monthly contracted electricity output of the power plant (kWh); QdkM: Planned output according to the power system operation method updated next month of the power plant and converted to the delivery point (kWh); α: Proportion of electricity output paid according to the contract price applied for year N (%).Apply QcM = Max {QcttM; α × QdkM} (QcM: Monthly contracted electricity output of the power plant (kWh); QcttM: Minimum monthly contracted electricity output of the power plant (kWh) determined according to the provisions of Clause 2, Article 29 of this Circular; QdkM: Monthly planned output of coal-fired thermal power plants according to the power system operation method updated in the first month of each quarter (January, April, July and October) or of gas turbine plants according to the system operation method January and July power system or offshore wind power plant, new energy power according to monthly power system operation method and converted to delivery point (kWh); α: Proportion of power output paid according to contract price applicable to year N (%).
    Procedures for approving the next month's electricity market operation plan (Article 42.5)The Electricity Regulatory Authority appraises and approves the monthly electricity market operation planThe state electricity management agency is responsible for appraising and approving the monthly electricity market operation plan
    Real-time operation (Article 64.1)Decision on directive compliance with the Regulations on power transmission system issued by the Ministry of Industry and Trade.Decision on directive compliance with the Regulations on dispatching, operation, handling, troubleshooting, black start and restoration of the national power system issued by the Ministry of Industry and Trade.
    Determining market electricity price (Article 81)Scheduling market electricity price calculation in the modelNot considering thermal power plants that do not participate in market price in off-grid cycles.
    Data reconciliation (Article 76.2.c)- Before 12:00 on day D+4, relevant units shall check and compare metering data - Accept feedback on metering data reconciliation on the electricity market electronic information page.- Before 12:00 on day D+4, relevant units shall check and compare metering data, detect occurrences and events leading to output differences - Refuse to accept feedback on occurrences related to metering data of day D in case there is feedback from units on the electricity market electronic information page before 12:00 on day D+4
    Duration, effectiveness, and repeal of the Circular (Article 133)1. This Circular takes effect from November 25, 2024. 2. This Circular replaces Circular No. 45/2018/TT-BCT dated November 15, 2018 of the Minister of Industry and Trade regulating the operation of the competitive wholesale electricity market and amending and supplementing a number of articles of Circular No. 56/2014/TT-BCT dated December 19, 2014 of the Ministry of Industry and Trade regulating the method of determining electricity generation prices and the procedure for checking electricity purchase and sale contracts; Circular No. 24/2019/TT-BCT dated November 14, 2019 of the Minister of Industry and Trade amending and supplementing a number of articles of Circular No. 45/2018/TT-BCT dated November 15, 2018 of the Minister of Industry and Trade regulating the operation of the competitive wholesale electricity market and amending and supplementing a number of articles of Circular No. 56/2014/TT-BCT dated December 19, 2014 of the Minister of Industry and Trade regulating the method of determining electricity generation prices and procedures for checking electricity purchase and sale contracts, effective from January 1, 2020. 3. This Circular annuls Article 1 and Clause 3, Article 10 of Circular No. 12/2024/TT-BCT dated August 1, 2024 of the Minister of Industry and Trade regulating the amendment and supplement of a number of circulars Circular of the Minister of Industry and Trade related to the dispatch and operation of the national power system and the electricity market. 4. During the implementation process, if any problems arise, organizations and individuals are responsible for reporting to the Ministry of Industry and Trade for appropriate supplementation and amendment1. This Circular takes effect from February 1, 2025. 2. Circular No. 21/2024/TT-BCT dated October 10, 2024 of the Minister of Industry and Trade regulating the operation of the competitive wholesale electricity market is annulled. 3. The data and information including: ceiling price of electricity market, best new power plant, market capacity price, annual contract power output adjustment coefficient and power rate paid according to contract price approved by the Ministry of Industry and Trade in the 2025 Electricity Market Operation Plan will continue to be applied for the remaining months of 2025. 4. The Electricity Market Operation Plan for February 2025 approved by the Electricity Regulatory Authority according to the provisions of Circular No. 21/2024/TT-BCT will continue to be applied. 5. During the implementation process, if any problems arise, organizations and individuals are responsible for reporting to the Ministry of Industry and Trade for appropriate amendments and supplements.
    ### Removal points
    The following concepts and provisions are no longer mentioned in Circular No. 16/2025/TT-BCT, i.e. this Circular no longer regulates those issues:
    ◦ In the explanation of terms in Article 3 of Circular 21/2024/TT-BCT, there is no term: "Factory providing auxiliary services must develop and start up quickly according to the annually published list".

    ai-luatvietnam-icon-24 Change analysis