Decree No. 254/2025/NĐ-CPstatus2 - New regulations on payment and settlement of public investment projects (effective from September 26, 2025)

Effective date: 26-Sep-2025
Limitations
◦ Total Disbursed Capital (Article 6.4): The total disbursed capital for tasks and projects must not exceed the total investment level approved or adjusted by the competent authority.
◦ Capital Disbursed During the Year (Article 6.5): The amount of public investment capital disbursed for tasks and projects during the year must not exceed the total capital plan for the year allocated for each task and project (including the previous year's capital plan that is allowed to be extended and the advanced capital from the next year's state budget estimate).
◦ Exceeding Estimated Value/Contract/Compensation (Article 6.6): Public investment capital disbursed for each work and item of the task or project must not exceed the estimated value in the estimate information summary table (if self-implemented); must not exceed the contract value in the contract information summary table; must not exceed the compensation, support, and resettlement budget in the compensation, support, and resettlement information summary table.
◦ Exceeding the Planned Advance Capital (Article 9.4): Advance capital for all cases must not exceed the annual public investment plan allocated by the competent authority for the task or project.
◦ Exceeding the Advance Capital Use Period (Article 11.4): The advance capital use period of the state budget estimate for the following year shall not exceed December 31 of the following year, except in special cases decided by the Prime Minister or the Chairman of the People's Committee at all levels.
◦ Advance Capital After Deadline (Article 12.1): Annual planned capital for tasks and projects can only be advanced until December 31 of the planning year, except for compensation, support, and resettlement (until January 31 of the year following the planning year).
◦ Payment for Completed Volume After the Deadline (Article 12.2): The annual planned capital of the task or project is paid for the completed volume that has been accepted by December 31 of the planning year, the payment deadline for the completed volume is until January 31 of the year following the planning year.
### Need to know
◦ Using Capital for the Right Purpose (Article 6.1): The management and payment of public investment capital for tasks and projects must ensure the right purpose, right subjects, and compliance with regulations on public investment management, state budget and current laws.
◦ Opening an Account at the State Treasury (Article 5.1a): The investor of a task or project using public investment capital from the state budget must open an account at the State Treasury in a convenient place for transactions to make capital payments.
◦ Detailed Allocation of Planning Capital (Article 7.1a): Ministries, central agencies, and People's Committees at all levels must make detailed allocations of public investment planning capital from the state budget for each task and project according to prescribed criteria and send allocation plans to financial agencies at the same level.
◦ Assignment of Planned Capital Targets (Article 7.1b): Ministries, central agencies, and People's Committees at all levels must assign targets and detailed plan capital to investors for implementation, and send them to the payment agency where the transaction takes place.
◦ Contract Advance Payment Guarantee (Article 9.2a): For contracts with a contract advance payment value greater than 1 billion VND, a contract advance payment guarantee from the contractor or supplier is required with the value of each currency equivalent to the advance payment amount before the payment agency transfers the contract advance payment to the investor.
◦ Recovery of Advance Capital (Article 9.5): Advance capital must be recovered through payments for completed contract or estimate volumes, ensuring full recovery when the disbursement value reaches 80% of the contract or estimate value.
◦ Payment for Completed Volume According to Contract (Article 10.1a): Payment for completed volume is made based on the investor's proposal and the Contract Information Summary Table, and must be consistent with the contract type, contract price and contract conditions.
◦ Report on Advance Payment Status and Advance Recovery (Article 9.6b): The investor must prepare a report assessing the advance payment status and recovery of investment capital advances for each task and project and send it to the payment agency where the transaction takes place and relevant agencies.
◦ Submission of Annual Financial Report (Article 28): The investor must prepare an annual financial report and send it to the ministry, central agency or the investor's superior agency (in case of decentralized management) before May 1 of the year following the financial year.
◦ Auditing the Final Account Report (Article 34.3a): Important national projects and group A projects using public investment capital must have their final account reports audited upon completion before submitting them to competent authorities for review and approval of the final account (except for projects on the list of state secrets).
◦ Sending Decision Approving Settlement (Article 44.3): The decision approving the final settlement of investment capital for completed projects is sent to relevant agencies and units and to the Prime Minister and the Ministry of Finance (for important national projects, other important projects decided on by the Prime Minister for investment and group A projects using public investment capital).