Layout & language AEN
Sign in
Posted date: 25-Nov-2025 7:32:18 PM VN
Some new points of the:

Circular No. 12/2025/TT-BCT⚠️ - New regulations on determining electricity price and model power purchase agreement

on replacing of:
  • Circular No. 07/2024/TT-BCT⛔ - Methods for determining prices for electricity generation and power purchase agreement
Effective date: 01-Feb-2025
What's new
◦ Article 8. Power plants that do not have regulations on the method of determining the price of electricity generation services: This regulation specifies the handling method when a power plant does not have a method of determining the price or price framework for electricity generation. In this case, the buyer and seller of electricity will agree to develop a method of determining the price of electricity generation services that is suitable to the reality of the power plant, then report to the Ministry of Industry and Trade for consideration and guidance.
◦ Article 9. Temporary price: The regulation allows the seller and buyer of electricity to agree on a temporary price in case the official power purchase contract price has not been agreed upon.
◦ Article 11. Principles for determining electricity prices in bidding to select investors for power projects: When organizing bidding to select investors for power projects according to Clause 1, Article 19 of the Electricity Law, the electricity price in the bidding documents is built according to the principles in Chapter II of this Circular. The data set for calculating the proposed electricity price is based on the bidding documents and the consulting unit.
◦ Article 25. Responsibilities of fuel suppliers and transporters: Regulates responsibilities of fuel suppliers and transporters, requires compliance with the law, ensures fairness, competition and transparency in contract signing.
### Changes
FocusOld (Circular 07/2024/TT-BCT)New (Circular 12/2025/TT-BCT)
Subjects of application (Article 1)Clause 2, Article 1 of Circular 07/2024/TT-BCT generally states "Other relevant organizations and individuals".Point b, Clause 2, Article 1 of Circular 12/2025/TT-BCT is more specific: "Other relevant agencies, organizations and individuals".
Explanation of terms about Electricity Buyer (Article 2)Clause 2, Article 2 of Circular 07/2024/TT-BCT: The Buyer is Vietnam Electricity Group (or its representative unit according to hierarchy and authorization), Northern Power Corporation, Central Power Corporation, Southern Power Corporation, Hanoi Power Corporation, Ho Chi Minh City Power Corporation, large electricity users, other electricity wholesale units according to regulations of the electricity market.Clause 2, Article 2 of Circular 12/2025/TT-BCT: The Buyer is Vietnam Electricity Group (or its representative unit according to hierarchy and authorization), Northern Power Corporation, Central Power Corporation, Southern Power Corporation, Hanoi Power Corporation, Ho Chi Minh City Power Corporation, other electricity wholesale units according to regulations of the competitive electricity market. Eliminate "large electricity customers".
Principles for determining electricity generation service prices (Article 3)Clause 1, Article 3 of Circular 07/2024/TT-BCT: The electricity generation price of a power plant is built on the basis of reasonable and valid expenses of the Investor during the entire economic life of the project and the internal financial rate of return (IRR) does not exceed 12%. Clause 2: The electricity generation price of a power plant, including the following components: a) Power purchase contract price; b) Special connection price (if any).Clause 1, Article 3 of Circular 12/2025/TT-BCT: The electricity purchase contract price of a power plant is built on the basis of reasonable and valid expenses of the Investor during the entire economic life of the project and the internal financial rate of return (IRR) does not exceed 12%. Clause 2: The price of the electricity purchase contract is agreed upon by the electricity seller and the electricity buyer and is built according to the method prescribed in Article 4 of this Circular.
Method of determining average power generation for many years at the Power Delivery Point (AGN) (Article 5)Point c, Clause 2, Article 5 of Circular 07/2024/TT-BCT stipulates a more complicated way of calculating AGN, taking into account the power output at the power plant's output according to the basic design, generator terminal capacity, Tmax, self-consumption and loss ratio, and power reduction ratio.Point c, Clause 2, Article 5 of Circular 12/2025/TT-BCT is simpler: stating how to calculate AGN according to the formula (without stating a specific formula), and stipulating that in case AGN cannot be determined according to the formula, the two parties shall agree according to the basic design, technical design, documents of competent state agencies, or by agreement of the two parties. Additional provisions: (for wind power plants, the two parties shall agree to determine the output according to the expected level P50).
Loan interest rate (Point e, Clause 2, Article 5)Circular 07/2024/TT-BCT specifically regulates how to determine foreign currency and domestic currency loan interest rates.Circular 12/2025/TT-BCT stipulates similar regulations, but adjusts the semantics and may have some minor changes in the formula.
Adjustment of annual electricity generation service prices (Article 17)Clause 1, Article 17 of Circular 07/2024/TT-BCT: a) The components of the operation and maintenance price based on major repair costs and other costs are adjusted according to the average cost sliding rate specified in Appendix I issued with this Circular. The Seller and the Buyer shall study and propose a mechanism to adjust the components of the operation and maintenance price based on major repair costs and other costs for items originating from foreign currencies; b) The components of the operation and maintenance price based on labor costs are adjusted according to fluctuations in the regional minimum wage at the time of payment or according to the CPI index announced by the General Statistics Office but not exceeding 2.5%/year.Clause 1, Article 17 of Circular 12/2025/TT-BCT: a) The components of the operation and maintenance price according to major repair costs and other costs are adjusted according to the average cost sliding rate specified in Appendix I issued with this Circular. The electricity seller and the electricity buyer consider and agree on the mechanism for adjusting the components of the operation and maintenance price according to major repair costs and other costs for items originating from foreign currencies; b) The components of the operation and maintenance price according to labor costs are adjusted according to fluctuations in the regional minimum wage at the time of payment or according to the CPI index announced by the Central Statistics Agency but not exceeding 2.5%/year.
Article 21. Inspection of the power purchase contractArticle 21 of Circular 07/2024/TT-BCT: The Seller and the Buyer agree and are responsible for reporting to the Electricity Regulatory Authority to inspect the power purchase contract after completing negotiations and initialing the power purchase contract.Article 21 of Circular 12/2025/TT-BCT: This content is converted into Article 21. Responsibilities of the State management agency of electricity under the Ministry of Industry and Trade - Guide and inspect the implementation of the provisions of this Circular. If necessary, propose amendments and supplements to the Circular to suit practical needs and synchronization with legal regulations.
Documents proposing to negotiate power purchase contracts for new power plantsPoint d, Clause 1, Article 19 of Circular 07/2024/TT-BCT: Decision approving the initial total investment of the project or the adjusted total investment of the project in effect at the time of negotiating the power generation price and the main contents of the basic design of the investment project related to the negotiation of the power purchase contract, the basic design appraisal report and the document notifying the results of the basic design appraisal, the appraisal of the total investment of the state management agency on construction according to regulations (if any);Point d, Clause 1, Article 20 of Circular 12/2025/TT-BCT: The decision to approve the initial total investment of the project or the adjusted total investment of the project is effective at the time of negotiating the price of electricity generation services and the main contents of the basic design of the investment project related to the negotiation of the power purchase contract, the basic design appraisal report and the document notifying the results of the basic design appraisal, the appraisal of the total investment of the state management agency on construction according to regulations (if any);
Adjustment of electricity generation service prices (Article 26)No specific regulations.Circular 12/2025/TT-BCT: Supplement Article 26. Adjustment of electricity generation service prices - The electricity seller and the electricity buyer shall renegotiate the electricity generation service price in the signed electricity purchase contract according to the provisions of Clause 4, Article 52 of the Electricity Law.
Transitional provisions (Article 27)The content of the transitional provisions provides otherwise.Circular 12/2025/TT-BCT: Supplement Article 27. Transitional provisions - Changes to the transitional provisions.
Terms of entry into force (Article 28)The content of the transitional provisions stipulates otherwise.Circular 12/2025/TT-BCT: Supplement Article 28. Entry into force - Change provisions of entry into force, abolish Circulars.
### Removal points
◦ Special connection price (Article 8 of Circular 07/2024/TT-BCT): Circular 12/2025/TT-BCT no longer stipulates special connection price.
◦ Section 4. DOCUMENTS FOR NEGOTIATION OF ELECTRICITY PURCHASE AND SALE CONTRACT - Article 19. Documents for negotiation of electricity purchase and sale contract between the Seller and the Buyer Circular 07/2024/TT-BCT: Circular 12/2025/TT-BCT still regulates documents for negotiation of electricity purchase and sale contract, but has been changed to Article 20. Documents for negotiation of electricity purchase and sale contract between the seller and the buyer
◦ Chapter III INSPECTION OF ELECTRICITY PURCHASE AND SALE CONTRACTS Circular 07/2024/TT-BCT: Circular 12/2025/TT-BCT no longer regulates the chapter on inspection of electricity purchase and sale contracts.
◦ Article 22. Responsibilities of the Electricity Regulatory Authority: Circular 12/2025/TT-BCT no longer stipulates the responsibilities of the Electricity Regulatory Authority.
◦ Article 23. Responsibilities of Vietnam Electricity Group: Circular 12/2025/TT-BCT still stipulates the Responsibilities of Vietnam Electricity Group, but has been changed to Article 22. Responsibilities of Vietnam Electricity Group
Note: This analysis is based on a direct comparison of the contents of the two documents and may require further review of relevant legal documents for a full assessment.

ai-luatvietnam-icon-24 Change analysis

Found 644 posts Export list to Excel