Layout & language BEN
Sign in
Posted date: 25-Nov-2025 7:34:26 PM VN
Some new points of the:

Circular No. 09/2025/TT-BCT⚠️ - Method of determining the electricity generation price bracket and electricity import price bracket from February 1, 2025

on replacing of:
  • Circular No. 20/2024/TT-BCT⛔ - New method for establishing the generation price framework
  • Circular No. 19/2023/TT-BCT⛔ - Methods for determination of solar power and wind power generation pricing framework
  • Circular No. 31/2022/TT-BCT⛔ - Amendments to methods for determining electricity generation price range and electricity generation price
  • Circular No. 15/2022/TT-BCT⛔ - Methods for determining electricity generation price range of solar power plants and wind power plants
  • Circular No. 57/2014/TT-BCT⛔ - Guidelines on method of formulation of electricity generation cost frame
Effective date: 01-Feb-2025
What's new
◦ Expanded scope of regulation (Article 1): Circular 09/2025/TT-BCT expands the scope of regulation, including:
◦ Detailed regulations on documents, procedures, and processes for developing and approving the electricity import price framework and methods for developing the electricity import price framework according to Clause 5, Article 46 of the Electricity Law No. 61/2024/QH15.
◦ Applicable to domestic organizations that import electricity from Laos and China.
◦ Explanation of new terms (Article 2): Circular 09/2025/TT-BCT adds explanations for new terms, reflecting the development of the electricity industry:
◦ Calculation parameters set.
◦ Power system and electricity market operator.
◦ Pumped storage hydroelectric power plant.
◦ Floating solar power plant.
◦ Ground-mounted solar power plant.
◦ Onshore wind power plant.
◦ Principles for establishing electricity generation price framework for solar power plants by region (Article 3.4): The Circular stipulates that the electricity generation price framework for solar power plants is built based on the average annual radiation intensity of 03 (three) regions: the North, the Central and the South.
◦ Regulations on renewable energy power plants with electricity storage systems (Article 3.6): The Circular clearly stipulates how to calculate the total investment level when calculating the electricity generation price frame for renewable energy power plants that use combined electricity storage systems.
◦ Variable price for pumped storage hydropower plants (Article 6.4): The Circular stipulates that the variable price is a component to recover water storage costs determined by the electricity output consumed during the water storage cycle, the off-peak electricity retail price applied to manufacturing industries as prescribed and the cost of purchasing reactive power.
◦ Method for determining electricity import price framework (Article 9): The Circular specifically stipulates the method for determining electricity import price framework from Laos and China, including the following cases:
◦ As stipulated in international treaties.
◦ Import electricity from power plants.
◦ Import electricity through the national grid.
◦ Documents, order and procedures for approving the electricity import price framework (Article 11): The Circular clearly stipulates the steps, time and responsibilities of relevant parties in establishing, appraising and approving the electricity import price framework.
### Changes
FocusOldNew
Subjects of application (Article 1)Circular 57/2014/TT-BCT: "Power generation units owning power plants connected to the national power system with a total installed capacity of over 30MW..."Circular 09/2025/TT-BCT: "Agencies, organizations and individuals owning power plants operating in the territory of the Socialist Republic of Vietnam connected to the national power system, except for multi-purpose strategic hydropower plants, small renewable energy plants applying the avoided cost price list, power plants and generators providing ancillary services; power plants applying the electricity purchase price mechanism in documents of competent authorities..."
Calculation parameters (Article 5.4)There are no specific regulations on the basis for determining the calculated investment rate.Circular 09/2025/TT-BCT: The calculated investment rate is determined according to one of the following bases: the investment rate of the power plant with the selected calculated capacity value; the average investment rate of power plants with the same technology type; actual data on power purchase contract negotiations; or reference data from consulting organizations.
Average delivered power (Article 5.6)For solar and wind power plants in Circular 15/2022/TT-BCT, the average delivered power is determined based on specific parameters such as total area of photovoltaic panel installation, average annual radiation intensity, photovoltaic panel conversion efficiency, solar power plant efficiency, and wind power plant capacity factor.Circular 09/2025/TT-BCT provides more detailed regulations on how to determine the H parameter (average annual radiation intensity) for solar power plants in the North, Central, and South regions, based on information on basic surveys of renewable energy resources announced by competent authorities. At the same time, the circular supplements regulations on how to determine the average delivered power for pumped storage hydropower plants based on the power system demand and the amount of water pumped into the reservoir in the Feasibility Study Report.
Main fuel price (Article 6.2)Circular 31/2022/TT-BCT stipulates the main fuel price (Pnlc) for coal-fired thermal power plants and combined-cycle gas turbine plants using natural gas and LNG.Circular 09/2025/TT-BCT supplements regulations on main fuel prices for waste-to-energy power plants (electricity produced from waste), in which Pnlc takes into account subsidies from fuel collection, transportation and treatment in accordance with the law on environmental protection.
Document for approval (Article 12)Circular 57/2014/TT-BCT provides general regulations on documents for approval of electricity generation prices.Circular 09/2025/TT-BCT provides more detailed regulations on documents for approval of electricity generation price framework, including submission form, parameter table, calculation documents, and requires direct submission of 01 set of documents in the form of data message and direct submission of 01 set of documents in paper form (if necessary).
### Removal points
◦ Specific regulations on Standard Power Plants according to capacity ranges (Article 4 of Circular 57/2014/TT-BCT): Circular 09/2025/TT-BCT no longer specifically regulates Standard Power Plants according to capacity ranges as Circular 57/2014/TT-BCT. Instead, Circular 09/2025/TT-BCT only mentions Standard Power Plants as a general concept for calculating the electricity generation price framework.
◦ Specific parameters in the Appendix of Circular 57/2014/TT-BCT: Circular 09/2025/TT-BCT no longer stipulates specific parameters (such as Tmax, loan ratio, operating and maintenance cost ratio, fuel consumption rate...) in the Appendixes like Circular 57/2014/TT-BCT. Instead, Circular 09/2025/TT-BCT stipulates that these parameters are determined on the basis of the Feasibility Study Report, basic design, or referencing data from consulting organizations.
◦ Regulations on average avoidable cost prices of the North, Central and South regions according to Circular 32/2014/TT-BCT (Article 9 of Circular 57/2014/TT-BCT): The method of determining the ceiling price of hydropower plants based on the average avoidable cost prices of the regions according to Circular 32/2014/TT-BCT has been eliminated. Instead, Circular 09/2025/TT-BCT stipulates that the maximum price is built on the basis of the annual avoidable cost price schedule according to the method prescribed in Article 8 of Circular 09/2025/TT-BCT.
◦ Regulations on the ratio of electricity produced by season and by hour during the year (Appendix 1 of Circular 57/2014/TT-BCT): Circular 09/2025/TT-BCT no longer specifically regulates the ratio of electricity produced by season and by hour during the year to determine the ceiling price of hydropower plants.
◦ Concept of "Refined capacity" (Article 2 of Circular 57/2014/TT-BCT): The concept of "Refined capacity" is no longer used and explained in Circular 09/2025/TT-BCT.
This analysis helps clarify changes in regulations on electricity generation price framework, showing updates and adjustments to suit the development situation of Vietnam's electricity industry.