Layout & language AEN
Sign in
Posted date: 22-Sep-2025 7:19:13 AM VN
Some amends and supplements of the

Decree No. 88/2024/NĐ-CP⚠️ - Compensation policy when land is expropriated from August 1, 2024

within:
  • Decree No. 226/2025/NĐ-CPstatus2 - Amendments to regulations on calculation of land prices, extension of land use term and competence to manage land
  • Effected from: 15-Aug-2025
    New additions
    • Article 7a: (Decree 226/2025/ND-CP) Handling cases where there is a decision on land recovery for project implementation but there is a change in planning, boundary markers, and route orientation. This allows the adjustment of the decision on land recovery, the decision on approving the compensation, support and resettlement plan to suit the actual situation when there is a change in planning during the construction process.
    • Article 14a: (Decree 226/2025/ND-CP) Compensation for crops and livestock. Clarify more about how to determine the compensation level for perennial trees harvested many times and the unit price of compensation for damage to crops and livestock.
    • (Article 19, Clause 1, Point d): (Decree 226/2025/ND-CP) Supplementing regulations on the number of people who are supported to stabilize their lives when recovering agricultural land. Stipulating the number of supported populations being those who share the same land use rights at the time of approval of the compensation plan and the demographics arising after the time of allocating agricultural land to households.
    • (Article 22, Clause 5): (Decree 226/2025/ND-CP) Supplementing regulations on households and individuals directly engaged in agricultural production being supported in training, occupational change and job search, including cases of eligibility for land use right certificates.
    • (Article 24, Clauses 5 and 6): (Decree 226/2025/ND-CP) Regulations on the allocation of residential land or sale, lease or lease-purchase of houses to households and individuals when the State recovers land attached to houses without being eligible for compensation for residential land, if there is no other place of residence in the commune-level area where the recovered land is located. Supplementing regulations on the priority order of selection of resettlement locations.
    Changes
    SpotlightOld (Decree 88/2024/ND-CP)New (Decree 226/2025/ND-CP)
    Remaining land investment costs (Article 17, Clause 4)In which: P: Remaining land investment costs; The expenses are determined on the basis of the dossier provided by the person whose land is recovered.In which: P: Remaining land investment costs; The above-mentioned P1, P2, P3 and P4 expenses must be converted in accordance with the market prices at the time of issuance of the decision approving the compensation, support and resettlement plan.
    Expenses for ensuring the organization of compensation, support and resettlement (Article 27, Clause 2)"The agency competent to approve the compensation, support and resettlement plan shall decide to approve the security expenses..."" The agency competent to approve the compensation, support and resettlement plan shall decide to approve the cost of security, enforcement tallying, and coercive land recovery."
    Expenses for the organization of compensation, support and resettlement (Article 27, Clause 7)The formulation, approval of cost estimates, use and settlement of costs... comply with the provisions of the law on the budget and the law on public investment.The formulation, approval of cost estimates, use and settlement of costs... comply with the provisions of the law on budget, the law on public investment and other relevant laws.
    Subjects of support (Article 8, Clause 5); (Article 15, Clause 2); (Article 24, Clause 2)"Areas with difficult socio-economic conditions and areas with extremely difficult socio-economic conditions are district-level administrative units, communes or villages, hamlets, hamlets, villages, villages, neighborhoods and similar residential areas..."" Areas with difficult socio-economic conditions and areas with extremely difficult socio-economic conditions are administrative units commune-level or villages, hamlets, hamlets, villages, villages, street population groups and similar residential areas..."
    Compensation, support and resettlement when the State recovers residential land specified in Article 98 of the Land Law; Clause 2, Points a, b, Article 11"In case of communes, wards and townships""Case commune-level"
    Repeal or Expiration
    There is no provision in Decree No. 226/2025/ND-CP that clearly states the annulment or expiration of part or all of Decree No. 88/2024/ND-CP. Decree No. 226/2025/ND-CP mainly focuses on amending and supplementing a number of articles of Decree No. 88/2024/ND-CP, Decree No. 71/2024/ND-CP, Decree No. 101/2024/ND-CP, Decree No. 102/2024/ND-CP, Decree No. 112/2024/ND-CP and Decree No. 151/2025/ND-CP, without directly annulling the effect of Decree No. 88/2024/ND-CP.
    Overview of the effects of differences
    The amendments and supplements in Decree 226/2025/ND-CP have a positive impact, clarifying regulations on compensation, support and resettlement, helping the implementation process become more transparent, fair and effective. In particular, the addition of regulations on handling cases of planning changes after land acquisition and how to determine compensation for crops and livestock that have not yet had a production process are important points, helping to solve problems arising in practice. Changing the competent authority and emphasizing the role of communes, wards and townships in identifying land-related issues shows the decentralization of management, creating conditions for localities to be more proactive in compensation and resettlement support.
    Posted date: 22-Sep-2025 22 2025 7:19AM VN
    Some new points of the:

    Decree No. 88/2024/NĐ-CP⚠️ - Compensation policy when land is expropriated from August 1, 2024

    on replacing of:
    • Decree No. 06/2020/NĐ-CP⛔ - Amendments to regulations on elaboration of policy framework for compensation upon land expropriation
    Effective date: 01-Aug-2024
    What's new
    The completely new regulations are only available in Decree No. 88/2024/ND-CP (not included in the replaced documents):
    • Article 3. Formulation, appraisal and approval of compensation, support and resettlement plans: Detailed regulations on the contents of compensation, support and resettlement plans, including detailed plans for each person with recovered land and property owners (Clauses 1 and 2). Clearly stipulate the time limit for appraisal of the plan (not exceeding 30 days) and the appraisal dossier (Clause 3). Clearly state the responsibilities of competent agencies, organizations and persons in formulating, appraising and approving the plan (Clause 4).
    • Article 4. Compensation in land with a different use purpose than the recovered land or in houses when the State recovers land specified in Clause 1, Article 96, Clause 1, Article 98, Clause 1, Article 99 of the Land Law: Specific provisions on land prices for calculation of land use levies, land rent when compensation is made with land for other purposes (Clause 1). Clearly stipulating how to handle the difference in value between compensation and support for land and land use levy, payable land rent or house purchase money (Clause 2).
    • Article 5. Other cases of land compensation and conditions for land compensation specified in Clause 3, Article 95 of the Land Law: Clarification of cases in which households and individuals are using land without papers, committing violations, being assigned improperly but still receiving compensation (Clause 1, 2, 3, 4, 5).
    • Article 6. Compensation for land when the State recovers land in case the actual measured area is different from the area stated in the land use right papers: Specifying the method of handling compensation when there is a difference between the actual measured area and the paper (Clause 1, 2, 3).
    • Article 7. Compensation, support and resettlement upon land recovery by the State in special cases: Allowing provincial-level People's Committees to submit to the People's Councils of the same level for decision on specific policies on compensation, support and resettlement for investment projects specified in Clause 1, Article 92 of the Land Law (Clause 1). Specific provisions on compensation and support upon land recovery of people's armed forces units (Clause 2). Specific provisions on compensation and support for cases of land recovery due to the risk of threatening human life or the inability to continue using it (Clause 3).
    • Article 8. Compensation for land for households and individuals using land with houses, houses and works in service of life, households and individuals using residential land in areas with difficult socio-economic conditions or areas with extremely difficult socio-economic conditions before July 1, 2014 without papers on the right to use land use: Detailed regulations on compensation for each period of land use (before 18/12/1980, from 18/12/1980 to 15/10/1993, from 15/10/1993 to 01/7/2014), including residential land areas and other land (Clauses 1, 2, 3).
    • Article 9. Compensation for land for households and individuals who are using land for housing and violate the land law before July 1, 2014: Clearly stipulating the land area to be compensated depending on the time of stable land use (before 15/10/1993, from 15/10/1993 to 01/7/2014) and the encroachment after 01/7/2014 will not be compensated (Clause 1, 2, 3, 4).
    • Article 10. Compensation for residential land for households and individuals who are using land allocated in contravention of their competence before the effective date of the Land Law: Detailed provisions on compensation for each stage of land use (before 15/10/1993, from 15/10/1993 to 01/7/2004, from 01/7/2004 to before the effective date of the Land Law) (Clause 1, 2, 3, 4).
    • Article 11. Compensation for land when the State recovers residential land specified in Article 98 of the Land Law: Clearly stating the forms of compensation (residential land, houses, money, land for other purposes) and specific conditions when recovering all residential land or the rest is not eligible (Clause 1, 2).
    • Article 12. Compensation for land for households and individuals using land for purposes in the agricultural land group: Detailed regulations on compensation for each case of land use (without papers, violated, assigned improperly), the compensation area does not exceed the agricultural land allocation quota (Clause 1, 2, 3).
    • Article 13. Compensation for non-agricultural land other than residential land when the State recovers land: Detailed provisions on compensation for each case of land use (without papers, violations, assigned improperly) (Clauses 1, 2, 3).
    • Article 14. Compensation for damage to houses and construction works attached to land when the State recovers land: Detailing the formula for calculating the existing value of damaged houses and works (Clause 1).
    • Article 15. Compensation and support due to the relocation of graves when the State recovers land: Regulations on the arrangement of land funds in cemeteries, compensation and support expenses, and handling of cases where there are no relatives to relocate (Clauses 1, 2, 3).
    • Article 16. Compensation for self-renovation and repair of houses for current users of state-owned houses within the scope of land recovery to be demolished: Regulations on compensation for self-renovation and repair of state-owned houses (Clause 1).
    • Article 17. Compensation for the remaining land investment expenses when the State recovers land: Detailed regulations on compensated land investment expenses, conditions for determining expenses, dossiers, supporting documents and calculation formula (Clauses 1, 2, 3, 4, 5, 6).
    • Article 18. Compensation and support for damage to land in work safety protection corridors, protection areas, safety belts when building works, areas with safety protection corridors: Detailed regulations on compensation when changing land use purposes, not changing the purpose but limiting the ability to use, and compensation for houses and construction works (Clauses 1, 2, 3, 4).
    • Article 19. Support for life stabilization when the State recovers land: Detailed regulations on subjects, duration and level of life stabilization support (Clauses 1, 2).
    • Article 20. Support for stabilization of production and business when land is recovered by the State: Detailed regulations on subjects, conditions and forms of support for stabilization of production and business (Clauses 1, 2, 3, 4, 5, 6).
    • Article 21. Assist in relocating pets; support for dismantling, demolition and relocation of land-attached assets that are parts of construction works under construction permits with a definite term according to the law on construction but by the time of land recovery the permits have expired: Regulations on support for relocation of livestock and support for dismantling, demolition of construction works with expired permits (Clauses 1, 2).
    • Article 22. Support for training, occupational change and job search for households and individuals when the State recovers land: Detailed regulations on subjects eligible for support for training, occupational change and job search (Clauses 1, 2, 3, 4).
    • Article 23. Resettlement support when the State recovers land: Regulations on resettlement support for people who take care of their own accommodation (Clauses 1, 2).
    • Article 24. Resettlement arrangement: Detailed regulations on the minimum resettlement rate and forms of resettlement arrangement (Clauses 1, 2, 3, 4).
    • Article 25. Payment of compensation, support and resettlement: Detailed regulations on deduction of unfulfilled financial obligations, payment of value difference, and handling of compensation when there is a dispute (Clauses 1, 2, 3, 4, 5).
    • Article 26. Debiting land use levy when being allocated land for resettlement: Regulations on subjects eligible for land use levy debit, land price for debit, debit amount, and debt payment conditions (Clauses 1, 2, 3, 4, 5).
    • Article 27. Expenses for ensuring the organization of compensation, support and resettlement: Detailed regulations on the content of expenses, estimation, approval, use and settlement of expenses (Clauses 1, 2, 3, 4, 5, 6, 7, 8).
    • Article 28. Funding for compensation, support and resettlement: Regulations on funding sources, responsibilities for ensuring funding and cases where the investor voluntarily advances compensation (Clauses 1, 2).
    Changes
    SpotlightOld (Decree 47/2014/ND-CP)New (Decree 88/2024/ND-CP)
    Compensation, support and resettlement policy framework (Article 17)The policy framework includes: the area of each type of land expected to be recovered; the number of land users in the area where the land is expected to be recovered; expected compensation and support levels for each type of land recovery object...The policy framework includes: The area of each type of land expected to be recovered; The number of organizations, households and individuals using land in the area where the land is expected to be recovered; Expected compensation and support levels for each type of land recovery subject...
    Competence to approve compensation, support and resettlement plans (Article 17)Ministries and sectors having investment projects shall formulate, appraise and approve compensation, support and resettlement plans for the entire project.Based on the investment projects already decided and approved by the National Assembly and approved by the Prime Minister, the provincial-level People's Committees shall consider and submit to the People's Councils of the same level for decision on specific policies.
    Life stabilization support (Article 19)There is no specific level of support for a population, only stated that it is "equivalent to 30 kg of rice in 01 month according to the average price at the time of local support".The level of support for a population specified at Points a and b of this Clause is calculated in cash equivalent to 30 kg of rice in 01 month according to the average price at the time of local support.
    Supporting the stabilization of production and business when the State recovers landAfter-tax income is determined on the basis of audited financial statements or approved by tax authorities; in case it has not been audited or approved by the tax authority, the determination of after-tax income shall be based on the after-tax income declared by the unit in the financial statement and report on production and business results at the end of each year sent to the tax authority.After-tax income is determined as income after personal income tax and corporate income tax have been paid in accordance with the law on personal income tax and corporate income tax.
    Expenses for organizing compensation, support and resettlement (Article 31)Funding for the organization of compensation and ground clearance shall be deducted not more than 2% of the total compensation and support funding of the project.There is no specific deduction of 2%, instead, more detailed regulations on cost contents and the preparation and approval of estimates.
    Concentrated resettlement area project (Article 26 of Decree 47/2014/ND-CP)For projects of concentrated resettlement areas with phased construction according to component projects, the progress of land recovery and completion of construction of houses or infrastructure of the resettlement area shall comply with the schedule of each component project but the infrastructure works of each component project in the resettlement area must ensure the connection in accordance with the detailed planning approved by the competent state agency.The resettlement area is set up for one or more projects; houses and residential land in the resettlement area shall be arranged according to many houses and different levels of area suitable to the compensation levels and affordability of the resettled persons.
    Removal points
    Provisions contained in Decree 47/2014/ND-CP but no longer mentioned in Decree 88/2024/ND-CP:
    • Article 34. Handling of a number of issues arising when promulgating the Decree (Decree No. 47/2014/ND-CP): Regulations on handling cases of land transfer and land recovery due to violations and projects for which land recovery decisions have been issued before 01/7/2014.
    • Article 21. Support for training, occupational change and job search in case the State recovers residential land in combination with business and services of households and individuals who have to relocate: There are no separate regulations on support for training, occupational change and job search for cases of recovery of residential land in combination with business, services, which may be generally regulated in the regulations on supporting the stabilization of production and business.
    • Article 24. Support when recovering public land of communes, wards and townships (Decree No. 47/2014/ND-CP): Decree No. 88/2024/ND-CP does not mention specific support for cases of public land recovery of communes, wards and townships.