Some new points of the:

Circular No. 09/2026/TT-BNNMT - Amendments and supplements to a number of regulations on environmental impact assessment

on replacing of:
  • Circular No. 07/2025/TT-BNNMT⛔ - Adjustment of management competence in the field of environment
Effective date: 29-Jan-2026
What's new
These are completely new regulations, supplemented and only available in Circular No. 09/2026/TT-BNNMT that Circular No. 07/2025/TT-BNNMT does not mention.
1. Detailed process of organization of appraisal of environmental impact assessment (EIA) reports: Circular 09/2026/TT-BNNMT adds a series of new provisions to specify and detail the appraisal of EIA, including:
Article 13a (supplemented in Article 4 of Circular 09/2026/TT-BNNMT)*: Regulations on appraisal activities, appraisal time limit for each project group, detailed appraisal contents, and regulations on actual survey of the project area.
Article 13b (supplemented in Article 5 of Circular 09/2026/TT-BNNMT)*: Detailing the organization of EIA appraisal in the form of the establishment of a council, including responsibilities, composition, meeting conditions, working principles and appraisal results of the council.
Article 13c (supplemented in Article 6 of Circular 09/2026/TT-BNNMT)*: Regulations on the organization of EIA appraisal in the form of expert consultation, applicable to special public investment projects, including the process, responsibilities and methods of determining appraisal results.
Article 13d (supplemented in Article 7 of Circular 09/2026/TT-BNNMT)*: Regulations on the approval of EIA appraisal results, including the time limit for issuing decisions, time limits for project owners to edit and supplement reports and procedures for returning results.
2. Detailed process of issuance of environmental permits (GPMT): Circular 09/2026/TT-BNNMT supplements new regulations, systematizes the entire process related to environmental clearance.
Article 18a (supplemented in Article 9 of Circular 09/2026/TT-BNNMT)*: Detailing the main contents of the report on the proposal for the issuance of environmental clearance for 3 different subjects: (1) the project has a decision approving the EIA appraisal results, (2) the project is not subject to the EIA, and (3) the facility is in operation.
Article 18b (supplemented in Article 10 of Circular 09/2026/TT-BNNMT)*: Regulations on dossiers, order and procedures for issuance of environmental permits, including the time of submission of dossiers, the time limit for licensing, the appraisal process (establishment of a council or inspection team), and simplified procedures for special public investment projects.
Article 18c (supplemented in Article 11 of Circular 09/2026/TT-BNNMT)*: Regulations on dossiers, order and procedures for issuance, adjustment and re-issuance of licenses.
3. Regulations on waste management after treatment and in specific cases:
Article 38a (supplemented in Article 20 of Circular 09/2026/TT-BNNMT)*: New regulations on the management of products obtained from the process of recycling and waste treatment when put on the market; technical requirements for the use of inorganic waste for the production of non-fired bricks and requirements for the disposal of waste by co-treatment.
4. Other supplementary and detailed regulations:
Clause 9, Article 32 (supplemented in Article 15 of Circular 09/2026/TT-BNNMT)*: Regulations on the closure of domestic solid waste landfills combined with ordinary industrial solid waste landfills shall comply with general regulations.
Clause 5, Article 33 (supplemented in Article 16 of Circular 09/2026/TT-BNNMT)*: Stipulating that the use of ordinary industrial solid waste as production materials must be stated in the decision approving the results of EIA or GPMT appraisal.
Clause 8, Article 36 (supplemented in Article 18 of Circular 09/2026/TT-BNNMT)*: Stipulating detailed technical requirements for cocoon tanks for isolation and long-term storage of hazardous waste.
Changes
These are the same regulations mentioned in both Circulars but with changes and differences. The table below shows the changes of Circular No. 09/2026/TT-BNNMT compared to the provisions of Circular No. 07/2025/TT-BNNMT.
SpotlightOld (According to Circular No. 07/2025/TT-BNNMT)New (According to Circular No. 09/2026/TT-BNNMT)
Agencies receiving reports on environmental protection of investment project owners and establishmentsThe project owner shall send a report to: The environmental permit-granting agency (or the agency receiving environmental registration); Department of Agriculture and Environment; Commune-level People's Committees; investors in industrial park infrastructure. (According to Clause 3, Article 4 of Circular 07/2025/TT-BNNMT, amending Point a, Clause 5, Article 66).An additional receiving agency is added: the agency that has approved the results of the appraisal of the environmental impact assessment report. Other agencies remain the same. (According to Article 23 of Circular 09/2026/TT-BNNMT, amending Point a, Clause 5, Article 66).
Abolition of Forms in Appendix IIt only refers to the amendment and abolition of some phrases in Form No. 04 and Form No. 09. There is no mention of the complete abolition of other forms. (According to Clause 5, Point a, Article 4 of Circular 07/2025/TT-BNNMT).Completely annulling Form No. 06 and Form No. 07 in Appendix I. (According to Clause 7, Point a, Article 26 of Circular 09/2026/TT-BNNMT).
Abolition of Forms in Appendix IIThere is no provision for the abolition of these forms.Completely annulling Forms No. 26, 27, 36 and 38 in Appendix II. (According to Clause 8, Point g, Article 26 of Circular 09/2026/TT-BNNMT).
EnforcementThe Circular takes effect from July 1, 2025. (According to Clause 1, Article 6 of Circular 07/2025/TT-BNNMT).This Circular takes effect from January 29, 2026. At the same time, at this time, Circular No. 07/2025/TT-BNNMT expires. (According to Clauses 1 and 2, Article 28 of Circular 09/2026/TT-BNNMT).
Removal points
These are the concepts or regulations contained in Circular No. 07/2025/TT-BNNMT but Circular No. 09/2026/TT-BNNMT does not mention or abolish it explicitly.
1. Regulations related to climate change response:
◦ Circular No. 07/2025/TT-BNNMT devotes the entire Article 3 to amend and supplement a number of articles of Circular No. 01/2022/TT-BTNMT detailing the implementation of the Law on Environmental Protection on responding to climate change.
In contrast, Circular No. 09/2026/TT-BNNMT does not mention at all the contents related to responding to climate change or amending Circular No. 01/2022/TT-BTNMT. This shows that the scope of Circular 09/2026/TT-BNNMT focuses mainly on general regulations on environmental protection (EIA, land clearance, waste management, etc.) without including the field of climate change.
2. Abolition of a series of detailed regulations on waste management:
◦ Article 25 of Circular No. 09/2026/TT-BNNMT has clearly abolished many regulations that were previously still in force (including regulations amended and supplemented by Circular No. 07/2025/TT-BNNMT), specifically:
◦ Article 8, Clause 1 and Clause 2: Regarding the form of the report on investigation and assessment of natural heritage.
◦ Article 36, Points a, b, c, Clause 1; Points a, b, dd, Clause 2; Point b, Clause 3; Clause 6; Points a, c, d, dd, e, h, i, Clause 7: A series of detailed regulations related to technical requirements and management requirements for storage facilities, equipment, and hazardous waste storage areas.
◦ Article 37, Clauses 1, 2, 3 and Points a, b, c, d, e, Clause 4: Regulations on dossiers, order and procedures for notification of cross-border transportation of hazardous waste.
◦ Article 38, Point d, Clause 2: Regulations on the provision of information related to cross-border transportation of hazardous waste.
◦ Article 39a: This entire provision is repealed.
In summary, Circular No. 09/2026/TT-BNNMT is a document with a very large scope of amendments and supplements, not only changing existing regulations but also systematizing the entire process of EIA appraisal and issuance of environmental clearance, and at the same time abolishing many detailed regulations that are no longer appropriate. and officially replace Circular No. 07/2025/TT-BNNMT when it takes effect.