Circular No. 19/2016/TT-BXD dated June 30th, 2016 of the Ministry of Construction on guidelines for implementation of some content of the Law on Housing and the Government's Decree No. 99/2015/ND-CP⛔
Posted: 13/7/2016 1:49:50 PM | Latest updated: 2/8/2024 1:13:05 PM (GMT+7) | Newsletter #:4029
Effective: 15-Aug-2016 Status: Expired on: 1-Aug-2024
LuatVietnam This Circular provides some provisions on housing, including: procedures for requesting approval of investment guidelines of a housing project; procedures for selection of investor in a commercial housing project; raising capital for commercial housing development; official residence development; sale, lease, lease purchase of state-owned relocation houses, state-owned social houses; ownership of housing in Vietnam by foreign entities; and transfer of commercial house sale contract)
Accordingly, the raising capital by collecting advances from buyers or tenants under contracts to buy or lease off-the-plan housing is only allowed upon the completion of the foundation a housing project. The completion of the foundation and foundation beam of a housing project or floor elevation of the lowest floor is considered completion of lowest floor of such project (Article 9)
Regarding quantity of houses of a housing project in Vietnam foreign entities may own, the determination is carried out as follows: foreign entities may own up to 30% of residential apartments of an apartment building. If an apartment building has many blocks, foreign entities may own up to 30% of residential apartments of each block. With respect to detached houses, foreign entities may own up to 10% of the houses or 250 houses of each project (Article 29)
Regarding transfer of a commercial house sale contract, under this Circular, the buyer of a house of the investor in a commercial housing project may transfer the sale contract to another entity as long as the application for the Certificate has not been submitted to a competent authority, whether the house has been received or not (Article 32)
This Circular shall take effect from August 15th, 2016.
The following documents shall be expired as from the effective date of this Circular: Decision No. 29/2001/QD-BXD⛔ dated November 19th, 2001; Decision No. 17/2006/QD-BXD⛔ dated June 7th, 2006; Circular No. 38/2009/TT-BXD⛔ dated December 8th, 2009 ; Circular No. 16/2010/TT-BXD⛔ dated September 1st, 2010; Circular No. 14/2013/TT-BXD⛔ dated September 19th, 2013; Circular No. 03/2014/TT-BXD⛔ dated February 20th, 2014; Circular No. 07/2014/TT-BXD⛔ dated May 20th, 2014.
 
Effective notes
  • See more the amendments, supplements at Circular No. 02/2019/TT-BXD⛔ dated July 1st, 2019; Circular No. 07/2021/TT-BXD⛔ dated June 30th, 2021.
  • Articles 4, 5, 6, 7, 8, clauses 1 Article 9, Article 11, contents relating to investment in the form of Build-Transfer (BT) at points b, c clause 2 Article 13, point b clause 2 Đ Article 17, the phrase “giá thuê mua” at clause 2 Article 20, clause 1 Article 21 and Annexes No. 02, 03, 04, 05, 06 of this Circular shall be abrogated from August 15th, 2021, according to the regulations at Circular No. 07/2021/TT-BXD⛔ dated June 30, 2021.
  • This Circular shall be expired from August 1st, 2024, replaced by Circular No. 05/2024/TT-BXD⚠️ dated July 31st, 2024.