stop-check Regulations on settlement of finished projects utilizing state capital English attachment

Circular No. 10/2020/TT-BTC dated February 20th, 2020 of the Ministry of Finance on settlement of finished projects utilizing state capital
Posted: 9/3/2020 3:10:00 PM | Latest updated: 1/12/2021 1:10:48 PM (GMT+7) | Newsletter #:4920
Effective: 10-Apr-2020 Status: Expired on: 1-Jan-2022
LuatVietnam According Article 4 of this Circular, with respect to important national projects and class A projects with multiple component projects, independent sub-projects: Prepare final account, appraise and approve settlement each component project or independent sub-project similar to an independent investment project.
With respect to projects in preparation phase: in case projects in preparation phase are provided with capital plans for investment in cost of approved investment projects, competent individuals capable of approving investment projects shall decide to perform separate settlement for projects in preparation phase or settlement along with investment projects. In case projects in preparation phase are provided with separate plans for allocating capital, perform settlement similar to independent sub-projects and consolidate project settlement.
In case compensation, assistance and relocation are turned into separate projects during approval of national important projects and class A projects: Prepare final accounts and reports on settlement appraisal similar to independent investment projects.
All national important projects and class A projects utilizing state capital must perform audit for final accounts of finished projects before presenting to competent authorities for appraisal and approval. For other projects, competent individuals capable of approving project investment shall consider and decide independent auditing bidders to conduct audit for final accounts of finished projects.
Period for project developers to produce settlement documents and request approval is 09 months (with regard to important national projects and class A projects), 06 months (with regard to class B projects), 04 months (with regard to class C projects) from the date on which acceptance records of projects, constructions are signed.
This Circular takes effect from April 10th, 2020.
To replace Circular No. 09/2016/TT-BTC⛔ dated January 18th, 2016 and Circular No. 64/2018/TT-BTC⛔ dated July 30th, 2018.
 
Effective notes
  • Please be noted that the attachments are neither translated nor included in the English file.
  • This Circular shall be expired from January 1st, 2022, replaced by Circular No. 96/2021/TT-BTC⛔ dated November 11th, 2021.