stop-check Operation process in the national power system

Thông tư số 44/2014/TT-BCT ngày 28/11/2014 của Bộ Công thương quy trình thao tác trong hệ thống điện quốc gia (36 trang)
Posted: 8/12/2014 2:57:28 PM | Latest updated: 14/2/2025 1:47:27 PM (GMT+7)
Effective: 23-Jan-2015 Status: Expired on: 1-Feb-2025
LuatVietnam This Circular prescribes the order of operation; basic operations of electrical equipment of power plants, power stations and power grids with a voltage of 01 kV or more in the normal operation mode of the national power system; regulations on the numbering of electrical equipment of power plants, power stations and power grids with a voltage of 01 kV or more.
Manipulation is the operation of changing the state of one or more devices in the electrical system for the purpose of changing the operating mode of that equipment
The operator mentioned in this Circular is the person tasked to operate electrical equipment, including:
a) Dispatchers at all dispatching levels;
b) Operators assigned to work at power stations;
c) Equipment operators assigned to work at power plants;
d) Operators assigned tasks at the control center;
dd) Staff on duty assigned at the distribution power grid.
The Circular takes effect from 23/01/2015 and replaces Decision No. 16/2007/QD-BCN dated 28/3/2007.
 
Effective notes
  • See more amendments and supplements in Circular No. 31/2019/TT-BCT⛔ dated 18/11/2019.
  • Expire from February 1, 2025, replaced by Circular No. 06/2025/TT-BCTstatus2 dated February 1, 2025.