stop-check Stricter rules to guarantee contractor performance English attachment

Decree No. 48/2010/ND-CP⛔ dated May 7, 2010 of the Government on contracts in construction activities
Posted: 31/8/2011 9:25:00 PM | Latest updated: 25/8/2022 9:08:50 AM (GMT+7) | Newsletter #:2494
Effective: 1-Jul-2010 Status: Expired on: 15-Jun-2015
LuatVietnam This Decree regulates the for contracts in construction activities with regards to the construction projects that use 30% of the state capital. For construction contracts under the projects using ODA capital, if the international treaties to which Vietnam is a member has other regulations with the provisions of this Decree shall comply with the provisions of the international treaties.
Some points to note in this Decree are as follows:
Contract price does not exceed the bid price (in case of bidding), not exceeding the approved estimate package (in case of contractor). The adjustment of prices and construction contract adjustment applies only during contract performance under the contracts signed. Where the adjustment does not change the investment objectives or do
not exceed the total approved investments, the investors may decide, contrary to reports from the competent authority to decide the investment decision. For package contract, the contract is adjusted only for the additional workload beyond the signed contract.
Decree also specified, the price adjustment contract only applies to contracts under fixed unit price, unit price adjustments and contract over time. This provision creates favorable conditions for investors to compare the regulations for the implementation of the contract price adjustments appropriately, to avoid price fluctuations due to stagnation of build.
Decree also stated that the contractor is responsible for warranty work, warranty and equipment in accordance with the agreement. For special projects and grade level, the warranty period of not less than 24 months from the date of acceptance of the works are put into use, the warranty is 3% of contract value. The work remaining warranty period of not less than 12 months, then the warranty rate is 5% of contract value.
Generally, investors must buy building insurance. Where the premium has been calculated into the contract, the contractor shall buy this insurance. Also, the contractor shall buy the insurance necessary to ensure their activities.
Decree takes effect from July 01st, 2010 and replace Decree 99/2007/ND-CP⛔ dated June 13th, 2007 of the Government on contracts in construction activities.
 
Effective notes
  • See more amendments and supplements at Decree No. 207/2013/ND-CP⛔ of December 11, 2013.
  • This Decree shall be expired from June 15, 2015, replaced by Decree No. 37/2015/ND-CP⛔ of April 22, 2015.